Byarma (Damoh-Patera) Multi Village Rural Water Supply Scheme, District. Damoh

Project Cost - Rs 447.59 Crores

Consultancy for the “Engineering, procurement, construction, testing, commissioning, trial run and operation & maintenance of various components of the project for ultimate capacity of bringing 59 MLD treated water (23 hours of pumping) from the Satdharu Dam on River Satdharu to 424 villages. of Damoh, Hatta, Jabera, Patera & Tendukheda Blocks of Damoh- District in Single Package on ‘Turn-key job basis’ including trial run and running & maintenance of the entire scheme for 10 years.

Read More....


Nagaur Lift Project, Phase-I, Package III

Project Cost - Rs 299.91 Crores

Consultancy for the “Work for construction of cluster distribution network, IEC activities, pump houses, clear water reservoirs, overhead service reservoirs, 33 KV Switchyards village distribution network under package-III of Nagaur Lift Project, Phase-I with Operation & maintenance of complete System for 10 Years on Single Point responsibility Turnkey Basis’’

Read More....


PMC phase-II, Ratangarh-Sujangarh section (Package-1)

Project Cost - Rs 234.65 Crores

Consultancy for the “Works related to Execution of up gradation work of Dhannasar, Sadasar, Pallu and Sardarshahar headworks, Construction of Pump house at proposed Ratangarh headworks, Providing, Installation, testing and commissioning of Pump sets at existing Sardarshahar headworks, providing, laying, jointing, trsting & commissioning of MS/DI pumping main from Sardarshahar to Ratangarh and Sujangarh, Construction of 6 nos. CWRs, development of SCADA system and other related Civil works on Single Point Responsibility basis turn key Job contract including necessary design, Operation and maintenance for ten years, under PMC phase-II, Ratangarh-Sujangarh section (Package-1).

Read More....


Regional water supply schemes of Kaman – Pahari Tehsils

Project Cost - Rs 227.27 Crore

Consultancy for the “Work of Regional water supply schemes of 246 villages and their NRVs & dhanies, of Kaman - Pahari Tehsils, under CDBP WS project and Augmentation of UWSS of Kaman town on Single responsibility turnkey basis i.e. Design, Build and Operation & Maintenance during defect liability period up to one year after completion of works and thereafter for 10 years (Package-I) .”

Read More...


Comprehensive WSS For Rajeev Gandhi Nagar, UWSS Kota

Project Cost - Rs 63.96 Crores

Consultancy for the Execution Of Comprehensive WSS For Rajeev Gandhi Nagar And Extension, Prem Nagar , Ipia ,Krishi Upaj Mandi , Ward No 5 , Lakawa Residential , RIICO Ranpur And Ranpur Uit, UWSS Kota On Single Responsibility Turn Key Basis With Five Year O&M.(Design ,Build, Operate And Maintenance Complete Work.)

Read More....


Cluster water supply system 92 villages of tehsil Laxmangarh District Sikar, Rajasthan

Project Cost - Rs 99.82 Crores

Consultancy for the “Work for construction of Cluster water supply system of 92 villages along with other habitations of tehsil Laxmangarh District Sikar to befed from Cluster Pumping StationLaxmangarh (Manasi) under Fatehpur –Laxmangarh Pkg-v Water Supply Project as perscope of work on Single Point Responsibility basis turnkey Job contract including necessary design, Operationand maintenance for ten years on Single Point responsibility Turnkey Basis’’

Read More....


Urban Water Supply Schemes for 23 towns under AMRUT/SMART City Mission

Project Cost - Rs 1100.0 Crores

Consultancy Services for Urban Water Supply Schemes for 23 towns namely, Ajmer, Udaipur, Bharatpur, Gangapur city, Dhoulpur, Bikaner, Sawai Madhopur, Jodhpur, Baran, Bundi, Jhalawar, Kota, Bhilwara, Beawar, Nagaur, Jaipur, Hindaun City, Churu, Sujangarh, Sikar, Bhiwadi, Alwar, Chittorgarh under AMRUT/SMART City Mission in Rajasthan

Read More....


Cluster water supply system 74 villages of tehsil Laxmangarh District Sikar, Rajasthan

Project Cost - Rs 87.7 Crores

Consultancy for the “Work for construction of “Cluster water supply system of 74 villages along with other habitations of tehsil Laxmangarh District Sikar to befed from Cluster Pumping Station Mangloona under Fatehpur –Laxmangarh PKG-IV Water Supply Project as per scope of work on Single PointResponsibility basis turnkey Job contract including necessary design, Operation and maintenance for ten years, on Single Point responsibility Turnkey Basis’’

Read More....


Cluster water supply system of 74 villages of tehsil Laxmangarh District Sikar – Pkg II

Project Cost - Rs 68.71 Crores

Consultancy for the “Work for construction of “Cluster water supply system of 74 villages along with other habitations of tehsil Laxmangarh District Sikar to be fed from Cluster Pumping Station Mangloona under Fatehpur –Laxmangarh PKG-II Water Supply Project as per scope of work on Single Point Responsibility basis turnkey Job contract Including necessary design, Operation and maintenance for ten years, on Single Point responsibility Turnkey Basis’’

Read More....


Gulendi Water Supply Project, Jhalawar, Rajasthan

Project Cost - Rs 37.56 Crore

Consultancy for the “Work for construction of Execution of the work of Raw Water Intake pump machinery With Raw Water Main, Treatment plant, 11/0.44KV sub station, Clear Water Reservoir, Clear water main, Pumping station, cluster rising mains, cluster distribution mains, cluster ESRs with associated civil, electrical and mechanical works, village distribution system etc. for Gulendi Water Supply Project on single responsibility turn key basis with five year O&M. District Jhalawar.

Read More....


Kalikhar Water Supply Project, Jhalawar, Rajasthan

Project Cost - Rs 45.15 Crores

Consultancy for the “Work for construction of Execution of the work of Raw Water Intake pump machinery With Raw Water Main, Treatment plant, 11/0.44KV sub station, Clear Water Reservoir, Clear water main, Pumping station, cluster rising mains, cluster distribution mains, cluster ESRs with associated civil, electrical and mechanical works, village distribution system etc. for Kalikhar Water Supply Project on single responsibility turnkey basis with five year O&M. District Jhalawar

Read More....


Regional Water Supply Scheme for 44 villages from Saipau, Bharatpur, Rajasthan

Project Cost - Rs 32.70 Crore

Consultancy for the “Work for construction of Work of Regional Water Supply Scheme for 44 villages from Saipau offtake under Chambal Dholpur Bharatpur Project with operation and maintenance for 10 years on Single Point Responsibility Turnkey basis

Read More....


Regional water supply scheme for Tehsil Nahtadwara, Rajsamand, Rajasthan

Project Cost - Rs 22.87 Crores

Consultancy for the “Work for Regional water supply scheme for coverage of left out problematic habitation of Tehsil Nahtadwara from Bagheri Ka Naka Project, District Rajsamand on single point responsibility turnkey basis i.e. design build and one year defect liability periods and 3 year operation and maintenance."

Read More....


Comprehensive sewerage project for Shri Ganaganagar town of Rajasthan

Consultancy for topographical survey, data collection, micro level and micro level population projections and design of collection system up to STP point, lift station and design of primary treatment with the objective of using the treated water for irrigation purposes.

Read More....


ADB funded sewerage project for Jhalawar and Jhalrapatan

Consultancy for topographical survey, data collection, design of collection system, preparation of construction drawings for sewers( L-sections), lift station structure, mechanical and electrical installations etc. for ADB funded sewerage project implemented by RUIDP for Jhalawar and Jhalrapatan

Read More....


ADB funded Waste water drainage project for Sardarshshar

Consultancy for preparation of design and construction drawings for screens, grit chamber and lift stations for 3 locations for the drainage project including mechanical and electrical installations

Read More....


Upgradation of 2 nos. 62.5 MLD ASP based STP

Upgradation of 2 nos. 62.5 MLD ASP based STP & creation of additional treatment capacity of 90MLD to treat a total of 215 MLD, Jaipur

Read More....


Bio-Mining

Bio-mining, stabilising and segregation of waste, and disposal of RDF, inert material and recyclable material, Jaipur

Read More....


Bisalpur – Prithviraj Nagar Water Supply

Work of Bisalpur- Prithviraj Nagar Water Supply Project Phase-I, Stage-I

Read More....


Bisalpur – Jaipur Water Supply

Work of Bisalpur-Jaipur Water Supply Project Stage-II (Phase-I)

Read More....


Hanumagarh – Water Supply Production & Distribution Network

Design, Construction of Work of Water Supply Production and Distribution Network Improvement with House Service Connections for Non-Revenue Water Reduction and Continuous Water Supply, Construction of Water Treatment Plant, Reservoirs, Pumping stations, and Allied works and Construction of Sewer Network with House Connections, Construction of Sewage Pumping Station, Sewage Treatment Plants, Effluent Reuse & Allied Works and Operation & Maintenance Services of the Entire System for 10 Years at Hanumangarh